Auditors found no significant weakness in the £138m Land East scheme but say paying for itself will be challenging. The council's accounts are disclaimed again.

The council’s plan for the £138 million Land East scheme to pay for itself “will be challenging to deliver”, its external auditors have said. Grant Thornton’s annual report on Sevenoaks District Council goes to the Audit Committee on Thursday 26 November.

The auditors looked hard at the scheme this year and found no significant weakness in how the council has run it. They praise the procurement and the loan arrangements, but make two recommendations for improvement.

The same report confirms the council’s accounts for 2025/26 will be “disclaimed” again. That means the auditors give no opinion on them, as they have for every year since 2020/21. (Grant Thornton, Auditor’s Annual Report 2025/26)

What Land East is

Land East of the High Street is the council-owned land behind the town centre. The scheme would replace the leisure centre and surface car parks with homes and a new leisure centre, along with public realm improvements. It also includes the renovation of 96 High Street, whose upper floors hold community uses. The council chose Wates as its development partner and agreed a loan of up to £40 million in July. (Sevenoaks Online, Land East loan approved)

Grant Thornton puts the project’s value at about £138 million. It calls it “substantial in the context of the Council’s overall operations”.

Why the auditors looked again

Partway through the year, the auditors flagged the scheme as a possible “risk of significant weakness”. They gave three reasons:

  • the scale and complexity of the project
  • extra spending the council approved to settle a legal challenge from an unsuccessful bidder, and the legal costs
  • the timing of the decision, so close to the planned reorganisation of Kent’s councils

They then reviewed the procurement, the borrowing, the council’s staffing for the project and the financial case. The work included interviews with officers and councillors.

What they found

Procurement: no significant weakness. The report says the procurement “was robust and effective”. It says the council “acted prudently” over the bidder’s challenge, using outside legal advice to reach “a pragmatic approach to settlement”. The report does not give the cost of the settlement.

Reorganisation: the auditors say the scheme falls within the government’s July 2025 guidance warning councils not to tie the hands of the unitary councils that replace them. They found the plans pre-dated reorganisation, which “influenced the timing, but it was not the driver of the decision”.

Who runs it: the council expected a new unitary council to finish the job after April 2028. That date has gone. The government withdrew its decision on new Kent councils on 29 October, so the council may have to deliver the scheme itself, or for longer than planned. The auditors found “potential for confusion” over the roles of several senior officers. They also say the risk register does not yet name who owns each risk.

The money: the auditors say the council “has not set out a timetable” for the scheme to become self-financing. They say its handling of a funding gap “suggests a squeeze” on the public parts of the project, especially late in the build. They single out 96 High Street, where work has been rephased.

The leisure centre gap

The report also returns to a risk raised in October, when the council said the leisure centre might have to close during the rebuild. (Sevenoaks Online, leisure centre could close during rebuild)

“A 12-month break in leisure provision could impact on usership on reopening, depressing earnings and putting at risk the Council’s borrowing against future centre income,” the auditors write. They add that the council “has invested in significant modelling” to test those assumptions.

The two recommendations

  • Officer governance: set out who directs and oversees the project, and plan for a handover to a new council if reorganisation restarts.
  • Accounting advice: take specialist advice early on how the scheme will show in the accounts, and build it into the medium-term financial plan.

The report notes the council “has confidence in the approach it has taken to ensure that the project is self-financing”, including through the loan agreement.

Accounts disclaimed for another year

Grant Thornton expects to issue a disclaimer of opinion on the 2025/26 accounts after Thursday’s meeting. (Grant Thornton, draft independent auditor’s report)

A disclaimer is not a finding of wrongdoing. Since 2024, the law has set “backstop” dates to clear the national backlog of council audits. If auditors cannot finish by the backstop, they must disclaim. Sevenoaks’ accounts for 2020/21 to 2024/25 were all disclaimed this way.

The auditors say it is not only about the backlog. They kept open a “significant weakness” first raised last year in how the council closes its accounts. Their findings include:

  • draft accounts arrived on 2 July, two days after the national deadline of 30 June
  • working papers did not always reconcile to the accounts, and the draft had “arithmetical and cross-referencing errors”
  • the fixed asset register still had a £1.86 million difference on vehicles, plant and equipment
  • the finance team was stretched after the previous Section 151 officer left in June, with the Head of Finance now covering both jobs

They also record progress. The council rebuilt its fixed asset register and fixed how it charges for loans to its companies. It has also hired more accountants. The next audit has a backstop of 30 November 2027, and the auditors say the council “must make substantial progress” before it prepares those accounts in March 2027.

What it means for residents

Nothing changes on the ground yet. The Land East plans are still being worked up with Wates. The auditors’ recommendations go to councillors, who can question Grant Thornton on Thursday.

The Audit Committee meets at 7pm on Thursday 26 November in the Council Chamber, Argyle Road. The public can attend, and the meeting is livestreamed on the council’s YouTube channel. (Sevenoaks District Council, Audit Committee 26 November 2026)

For the rest of this week’s meetings, including the Full Council vote on the Local Plan, see our council week ahead.